Montoursville
About This Project
Working as subcontractor to the bridge contractor, KW REESE crews realigned 600 feet of railroad track at the approaches to two new bridges, and laid all timber and rail across the bridges.
Project Purpose
In 2009 a flood washed out the bridge
Worth Noting
Despite steel erection delays that compressed the time frame from one month to two weeks. REESE crews completed the job on time.
Client
SEDA-COG Joint Rail Authority
Location
Montoursville, PA